Osaka Prefecture and the City of Osaka published a draft implementation agreement for the Osaka integrated resort (IR) on September 5, 2023, setting out the concrete plan for the project's opening1. The opening date moves from the originally planned "autumn to winter 2029" to "around autumn 2030," a revision of about one year1. The main cause given is the prolonged national review and delayed certification under the IR Development Act1.
- The draft agreement was published on September 5, 20231
- The opening date moves from "autumn to winter 2029" to "around autumn 2030"1
- The delay is attributed to prolonged national review and delayed certification under the IR Development Act1
The funding plan is about 550 billion yen in borrowing and about 720 billion yen in equity: MGM about 306 billion yen, Orix about 306 billion yen, and minority shareholders about 106 billion yen in total1. The two core shareholders, MGM and Orix, decided to make additional investments of about 95 billion yen each to cover the shortfall1.
The draft agreement also covers the operating structure, conditions for contract cancellation and measures for breach of the agreement2. The application to the national government has been agreed2. The prefecture and city plan to apply to the government, and if it passes review, the prefecture and Osaka IR Corporation (the SPC) aim to sign a formal agreement by the end of September1. The SPC separately signs a land leasehold contract with Osaka City1.
The SPC judged that the business preconditions were not met as of the judgment date and that it is not in a position to make a final decision on proceeding1. A cancellation right was set for the SPC, exercisable until the end of September 20261. The stated preconditions include tax treatment and Casino Management Committee rules ensuring international competitiveness and standards; financing, meaning a loan agreement and reasonable prospect of drawdown; development, meaning appropriate city measures on land and soil; and COVID-19, meaning a prospect of tourism demand recovery1.
Revised schedule1:
| Date | Stage |
|---|---|
| April 2023 | Area development plan certified |
| Spring 2023 onward | Administrative procedures and surveys |
| Summer 2023 | Approval of implementation agreement; signing of agreement and fixed-term business lease |
| Autumn 2023 | Start of liquefaction countermeasure work |
| Summer 2024 | Ordering and start of IR preparatory work |
| Spring 2025 | Ordering and start of IR construction work |
| Summer 2030 | Completion of construction |
| Autumn 2030 | Opening of IR facilities |
"開業予定の「2029年秋〜冬」から「2030年秋ごろ」に開業時期を1年程度見直しする事になりました"
What it means for players
The Osaka resort, which would be Japan's first casino-containing IR, will not open before around autumn 2030 on the current plan, roughly a year later than first announced1. Until then, casino gambling in Japan remains unavailable at an IR, and the rules on who may enter, what they may play and the charges inside have not been reported as finalized. The draft agreement sets out operating and cancellation terms but does not change the legal position for players in the meantime1. The SPC's cancellation right, exercisable until the end of September 2026, means the project could still be called off before construction is complete1.
What happens next
The prefecture and city apply to the national government for the agreement, and if approved, the prefecture and Osaka IR Corporation aim to sign it by the end of September 20231. Liquefaction countermeasure work is scheduled to start around autumn 2023, IR preparatory work around summer 2024, and construction around spring 2025, with completion around summer 20301. The SPC's cancellation right runs to the end of September 20261.
Sources2 sources
- 大阪IR開業は2030年秋にリスケ、政府の認定が遅れが主原因。初期投資額は約1兆2,700億円に増加、MGMとオリックスが自ら追加投資! | Re-urbanization -再都市化-, saitoshika-west.com
- 大阪IRの開業時期が延期される | まとめまとめ@最新ニュース, matomame.jp